机构地区: 国家电网公司中国电力科学研究院
出 处: 《电力建设》 2011年第11期55-58,共4页
摘 要: 针对某电厂饱和软粘土的特殊地质条件,分别采用强夯与强夯置换法进行了地基加固处理。详细介绍了设计方案,通过平板载荷试验、超重型动力触探试验、密实度试验等检测方法对地基加固效果进行综合评价分析,进一步验证了强夯与强夯置换法的适用条件,对此类工程的地基加固处理具有一定的参考意义。 Focusing on the saturated soft soil foundation in electric power plant,the dynamic compaction and dynamic replacement method are adopted.The design and execution process are introduced in detail.The reinforcing effects are comprehensively evaluated based on the results of plate loading test,super-heavy dynamic penetration test and density test.In addition,the applicable conditions for the dynamic compaction and dynamic replacement method are presented,that should be helpful to the design of similar projects.