机构地区: 汕头大学工学院土木工程系
出 处: 《施工技术》 1999年第3期50-51,共2页
摘 要: 某高层建筑采用滑模施工技术,中途发生阻滑事故。分析原因,主要是滑模设计不合理、没有严格遵守施工规范及商品混凝土性能不稳定等因素所致。 In this paper, an obstructing failure of sliding formwork for tall building construction has been introduced. The main factors of this incident are as follows namely: (1) improper formwork design, (2) not obeying the construction regulations strictly, (3) unstable quality of commodity concrete.[